Project goals
Supply and Installation of Lookout & Walking Track Balustrades & Bridges at Pulpit Rock Lookout at Blackheath
Scope
Pulpit Rock Lookout & Reserve were heavily impacted by the black summer bushfires in 2019/20 with the majority of visitor infrastructure being damaged or destroyed. This included over 300 metres of balustrade, over 400 timber steps, the toilets, shelters, picnic settings and signage.
Council has been undertaking an extensive, staged program of planning & repairs that will ensure the renewed infrastructure supports high-quality visitor and community experiences, and this staging has reflected the available resources and funding from a range of budgets.
The last of the bushfire damaged repair works required at Pulpit Rock Lookout & Reserve focus on the lookout & walking track balustrades & bridges for the lower area.
Requirements
Mandatory requirements
-
Scheme membership (SCM0256) *
Construction - InfrastructureThis procurement category has a mandated scheme.
This category has a mandated scheme, to be awarded this contract you may need to be a member of the Construction Scheme for works up to $1 million SCM0256.
Are you a member of SCM0256?
Response type
Radio button (Yes/No)
Opportunity requirements
Supply and Installation of Lookout and Walking Track Balustrades and bridges at Pulpit Rock Lookout, Blackheath
Pulpit Rock Lookout & Reserve were heavily impacted by the black summer bushfires in 2019/20 with the majority of visitor infrastructure being damaged or destroyed. This included over 300 metres of balustrade, over 400 timber steps, the toilets, shelters, picnic settings and signage.
Council has been undertaking an extensive, staged program of planning & repairs that will ensure the renewed infrastructure supports high-quality visitor and community experiences, and this staging has reflected the available resources and funding from a range of budgets.
The last of the bushfire damaged repair works required at Pulpit Rock Lookout & Reserve focus on the lookout & walking track balustrades & bridges for the lower area.
Response typeFree text
Evaluation
Weighting
The evaluation weighting is an estimate and is subject to change.
- Price
- 30%
- Non price
- 70%